Ain Sokhna Product Hub

Place of Works

Year of Completion

2017

Our scope of work for the Oil Jetty in Ain Sokhna included the construction of a 3,500-meter-long jetty founded on tubular steel piles. A total of 211 piles were driven to support the structure. The project also involved in-situ casting with steel reinforcement, the installation of precast concrete elements, and the placement of heavy-duty steel crossheads. The jetty was designed to meet high-performance and durability standards for oil terminal operations.

Scope of Works

  • Construction of 3500 m Jetty - on Piles
  • Driving of 211 Steel Tubular Piles (L - 72,00 m, OD - 1.40m, incl1:3)
  • Installation of Steel Reinf/ment & In-situ Casting
  • Installation of Precast Concrete Elements
  • Installation of Steel Crossheads